I-35 at SH 123

This project includes improving the SH 123 intersection and ramp reversals along I-35 between SH 80 and RM 12

Project Activity

  • Lane Closure

    There are no lane closures at this time.

Project Activity

Project activity includes improvements to the northbound and southbound I-35 frontage roads and bridges at the San Marcos River. TxDOT anticipates periodic closures of the river at I-35 to complete the work. Recreational users along the San Marcos River will be notified in advance of any closures via shore signs and can sign up for additional project updates.

Funding

  • Construction cost: $107 million funded by CAMPO and TxDOT 

Schedule

  • Construction start: August 2021
  • Anticipated construction completion: early 2025, weather permitting

Contractor

  • Webber, LLC

Project Map

Map of I-35 at SH 123

Milestones

Complete

Reconstruct southbound I-35 frontage road

  • Reconstruct the southbound I-35 frontage road north of SH 123, including the San Marcos River bridge
Complete

Reconstruct northbound I-35 frontage road

  • Reconstruct the northbound I-35 frontage road south of SH 123

Finalize Project

  • Perform final paving and striping