I-35 from Grand Avenue Parkway to SH 45 North

This project includes ramp reversals along northbound I-35 between Grand Avenue Parkway and SH 45 North

Project Activity

  • Lane Closure

    There are no lane closures at this time.

Funding

  • Construction cost: $8.2 million funded by CAMPO and TxDOT

Schedule

  • Construction start: August 2020
  • Anticipated construction completion: mid-2021, weather permitting 

Contractor

  • Jordan Foster Construction

Project Map

Map of I-35 from Grand Avenue Parkway to SH 45 North

Milestones

Set Up Work Zone

  • Place traffic barriers
  • Place temporary signage
  • Begin drainage work on the northbound I-35 frontage road

Reversing Entrance and Exit Ramps

  • Construct the new northbound I-35 exit ramp north of Grand Avenue Parkway and the new entrance ramp south of SH 45 North
  • Close the existing ramps
  • Install high-mast lighting

Construct Extended Entrance/Exit Lane

  • Construct extended entrance/exit lane on the northbound I-35 frontage road
  • Construct the extended entrance lane on the I-35 mainlanes under SH 45 North

Final Paving and Striping

  • Intersection widening at Picadilly Drive and the I-35 frontage road
  • Final paving and striping