I-35 from south of Loop 82 to north of River Ridge Parkway

This project reconfigures the northbound I-35 entrance ramp and adds a new exit between Loop 82 and River Ridge Parkway

Project Activity

  • Lane Closure

    There are no lane closures at this time.

Funding

  • Construction cost: $14 million funded by CAMPO and TxDOT

Schedule

  • Construction start: January 2021
  • Anticipated construction completion: mid-2022, weather permiting

Contractor

  • Hunter Industries, Ltd.

Project Map

Map of I-35 from south of Loop 82 to north of River Ridge Parkway

Milestones

Set up work zone

  • Place traffic barriers
  • Place temporary signage
  • Begin drainage work on the northbound I-35 frontage road

Construct mainlane and frontage road improvements

  • Install sound walls
  • Install retaining walls
  • Reconstruct the northbound I-35 mainlanes and frontage road

Reconfigure entrance/exit ramps

  • Reconstruct the northbound I-35 entrance ramp, south of Loop 82
  • Construct new northbound I-35 exit

Install corridor lighting

  • Install high-mast lighting
  • Reconstruct intersections at Crepe Myrtle Street and Hackberry Street

Final paving and striping

  • Complete final paving and striping