I-35 from RM 150 to Kyle Crossing

This project will reconfigure the northbound entrance/exit ramps between RM 150 and Kyle Crossing

Project Activity

  • Lane Closure

    Northbound I-35 frontage road left lane closed from RM 150 to Brent Boulevard

    Through January 2021

  • Lane Closure

    Northbound I-35 frontage road right lane closed from RM 1626 to Kyle Crossing

    Through December 2020

Funding

  • Construction cost: $21.9 million funded by CAMPO and TxDOT

Schedule

  • Construction start: September 2020
  • Anticipated construction completion: early 2022, weather permiting

Contractor

  • Hunter Industries, Ltd

       

Project Map

Map of I-35 from RM 150 to Kyle Crossing

Milestones

Construction between FM 1626 and Kyle Crossing

  • Reconstruct the northbound frontage road
  • Add an extended lane between ramps on the frontage road
  • Remove existing ramps and construct new ramps

Construction between RM 150 and FM 1626

  • Reconstruct the northbound frontage road
  • Reconstruct the Plum Creek bridge
  • Add an extended lane between ramps on the frontage road
  • Remove existing ramps and construct new ramps

Final paving and striping

  • Road sign installation 
  • Final paving operations
  • Final striping
  • Breakdown work zone