I-35 from RM 1431 to FM 3406 (northbound)

The project includes relocating an exit ramp on the northbound I-35 frontage road and adding an extended exit lane between RM 1431 and FM 3406

Project Activity

  • Lane Closure

    Northbound I-35 frontage road reduced to one lane from Jeffrey Way to the RM 1431 exit (#256)

    Through early 2021

Funding

  • Construction cost: $10.7 million

Schedule

  • Construction start: mid-2019
  • Anticipated construction completion: early 2021, weather permitting 

Contractor

  • Jordan Foster Construction

Project Map

Map of I-35 from RM 1431 to FM 3406 (northbound)

Milestones

Complete

Set up work zone

  • Place traffic barriers 
  • Place temporary signage
  • Install temporary drainage
Complete

Construct new exit ramp and extended exit lane

  • Construct new northbound I-35 exit ramp between RM 1431 and FM 3406
  • Construct the new extended exit lane on the northbound I-35 frontage road between RM 1431 and FM 3406
Complete

Close the old exit ramp

  • Close the old northbound I-35 exit ramp between RM 1431 and FM 3406 and open the new exit ramp to traffic

Convert frontage road from two to three lanes

  • Build out the left-hand side of the frontage road
  • Build out the right-hand side of the frontage road
  • Restripe frontage road to convert from 2 to 3 lanes

Finalize project

  • Road sign installation 
  • Final paving operations
  • Final Striping