I-35 at Ronald Reagan Boulevard

This project includes replacing the existing two-way bridge at Ronald Reagan Boulevard with two separate one-way bridges

Project Activity

  • Lane Closure

    Northbound I-35 reduced to one lane nightly at Ronald Reagan Boulevard

    Sunday, Oct. 13 through Thursday, Oct. 17 from 9 p.m. until 5 a.m.

  • Lane Closure

    Northbound I-35 reduced to one lane nightly at Ronald Reagan Boulevard

    Sunday, Oct. 13 through Friday, Oct. 18 from 9 p.m. until 5 a.m.

  • Lane Closure

    Northbound I-35 reduced to one lane nightly at Ronald Reagan Boulevard

    Sunday, Oct. 20 through Thursday, Oct. 24 from 9 p.m. until 5 a.m.

  • Lane Closure

    Northbound I-35 reduced to one lane nightly at Ronald Reagan Boulevard

    Sunday, Oct. 20 through Thursday, Oct. 24 from 9 p.m. until 5 a.m.

Funding

  • Construction cost: $13.6 million funded by CAMPO and TxDOT 

Schedule

  • Construction start: June 2019

  • Anticipated construction completion: mid-2021, weather permitting

Contractor

  • Dan Williams Company 

Project Map

Map of I-35 at Ronald Reagan Boulevard

Milestones

Set Up Work Zone

  • Place traffic barriers 
  • Place temporary signage

Open New Eastbound Ronald Reagan Boulevard Bridge

  • Construct new eastbound Ronald Reagan Bridge
  • Complete striping, bike lane and six-foot sidewalk
  • Open bridge to the traveling public

Open Westbound Ronald Reagan Bridge

  • Construct new westbound Ronald Reagan Bridge
  • Complete striping, bike lane and six-foot sidewalk
  • Open bridge to the traveling public

Demolish Old Ronald Reagan Bridge

  • Close old Ronald Reagan bridge to traffic
  • Demolish old bridge while new bridges are open to traffic
  • Clean up work zone and finalize project