I-35 at Williams Drive

The project includes the construction of a diverging diamond interchange at I-35 at Williams Drive

Project Activity

  • Lane Closure

    There are no lane closures at this time.

Funding

  • Construction cost: $61.7 million funded by CAMPO and TxDOT

Schedule

  • Construction start: October 2020
  • Anticipated construction completion: spring 2024, weather permitting

Contractor

  • J.D. Abrams L.P.

Project Map

Map of I-35 at Williams Drive

Milestones

Complete

Construct bypass lanes

  • Construct northbound and southbound I-35 bypass lanes

Construct Williams Drive bridge

  • Construct the I-35 at Williams Drive bridge to accommodate a diverging diamond intersection